SSD-9113 documentation
SHARE

State Significant Development approval SSD-9113

On 27 February 2019, the NSW Department of Planning, Industry and Environment (DPIE) approved the State Significant Development application (SSD-9113) for construction and operation of the Prince of Wales Hospital Acute Services Building comprising:
  • 13 storey acute services building (ASB)
  • overhead pedestrian links and helipad
  • excavation and associated site infrastructure and landscaping works
  • road upgrade works to Botany Street and Magill Street.

The planning approval is the result of a thorough assessment of the proposal and its environmental impacts.

The project EIS and supporting documentation is available on the DPIE Major Projects webpage.

Progress
Site preparation and early works for the Randwick Campus Redevelopment commenced in late 2018 under pre-existing planning approvals. Construction activity under SSD-9113 commenced in mid-2019 with bulk excavation and piling . Tower Cranes were established on site in late 2019, along with construction of the lift pits, inground services and ASB on-site detention system. Establishment of the jump form, and construction of basement slab and main structure is underway in early 2020.

Documentation
Environmental Impact Statement (link to Department of Planning and Environment Major Project's webpage)
1. Approved plans
2. Notice of decision
3. Development consent
4. Assessment report
5. Pre-construction compliance report | Compliance Construction Report No.1 | Compliance Construction Report No. 2
6. Community communication strategy 
7. Complaints register (issued monthly, combined for SSD-9113 and SSD-10339, as at 30 September 2020)
​8. Independent Audit Program

Independent Audit Report No.1 Sept 2019 Proponent Response to Independent Audit Report No.1
Independent Audit Report No.2 Jan 2020 Proponent Response to Independent Audit Report No.2    
Independent Audit Report No.3 July 2020 Proponent Response to Independent Audit Report No.3

9. Construction Monitoring Report (as at 8 March 2020)

Crown Certificates
Crown Certificate 1 Piling and Bulk Excavation (Certificate no. 19/124846-3) - May 2019
Crown Certificate 2 - Slab and Structure L01, Trenching and Inground Services, Lift Pits, Pile Caps, Stormwater Main Works, Cores/ Jump Form (Cerificate no. 19/124846-4) - October 2019
Crown Certificate 3 - Structure L02 - Roof, Services and fitout Level B2 - Level 01 and associated BCA, DDA, and FER - June 2020

Management plans and sub-plans

 Document name  Issue  Revision 1  Revision 2
 Construction and Environmental Management Plan  May 2019    
 Construction Traffic and Pedestrian Management Sub-Plan  May 2019  July 2019  April 2020
 Construction Worker Transportation Strategy  September 2019  April 2020  
 Noise and Vibration Management Plan  September 2019  May 2020  
 Construction Waste Management Sub-Plan   March 2019  September 2019  March 2020
 Construction Soil and Water Management Sub-Plan  March 2019    
 Flood and Emergency Response Management Sub-Plan  June 2019  September 2019  
 Heritage and Archaeological Management Plan  September 2019    
 Aboriginal Cultural Heritage Management Sub-Plan  June 2019